合成橡胶事业部SEBS脱盐装置工艺流程全部贯通,这标志着该项目已进入实质性攻关阶段。
新建脱盐装置引进了国外先进离心设备,采用自主创新技术,为确保试车顺利,该事业部组织车间技术骨干参与新装置试车,并邀请国外厂家指导试车工作。试车过程中,设备技术员人员认真检查脱盐装置各油泵油位,反复确认仪表、阀门正常,检查流程细节,详细记录试生产中发现的设备问题故障。同时,做好职工试车学习,组织操作人员向国外专家学习工艺操作方法。
目前,该事业部正对试车中遇到的不足进行整改优化,为装置一次成功开车做好充足准备。
橡胶脱盐过程的所有throughsynthetic橡胶SEBS的海水淡化装置分裂过程全部通过,标志着该项目进入了实质性研究阶段。在国外先进的离心设备引进新的海水淡化厂,自主创新技术的使用,以确保试验顺利进行,该部组织车间技术骨干参加新厂投产,并邀请外国厂商指导调试工作。在调试过程中,设备技术人员仔细检查泵除盐水平,再三确认仪表,阀门是否正常,检查过程的细节,测试设备故障问题在生产中发现,详细记录。同时,在学习做一个好工作,组织工作人员到国外专家研究的工艺操作方法。目前,分工不够满足装置优化精馏试验,做充分的准备,一个成功的驱动。
Baling Petrochemical rubber desalting process all through
Synthetic rubber division process SEBS desalination device all through, marking the project has entered a substantive research stage.New desalination plant in the introduction of foreign advanced centrifugal equipment, the use of independent innovation technology, in order to ensure the test smoothly, the Department organize workshop technical backbone to participate in the new plant commissioning, and invite foreign manufacturers guide commissioning work. During commissioning, equipment technician staff carefully check the pump demineralizer level, repeated confirmation instrument, the valve is normal, check the details of the process, a detailed record of test equipment failure problems found in production. At the same time, do a good job in learning, organization operation personnel to foreign experts to study the process operation method.At present, the division is insufficient meet test of the rectification for device optimization, a successful drive to do adequate preparation.All throughsynthetic rubber SEBS seawater desalination processes desalination device rubber division process all through, marking the project has entered a substantive stage of study. The introduction of new desalination plant in the centrifugal equipment advanced, the use of independent innovation technology, in order to ensure a smooth test, this organization workshop technicians to participate in the new plant put into operation, and inviting foreign manufacturers guide debugging. In the debugging process, equipment and technical personnel carefully check the pump to remove salt level, repeated confirmation instrument, the valve is normal, check the details of the process, test equipment failure problems found in production, a detailed record. At the same time, do a good job in the learning process, method of operation organization staff to foreign experts to study. At present, the division is not enough to satisfy the distillation optimization experiment device, make full preparations, a successful drive.